SMA ENERGY SYSTEM with SUNNY BOY STORAGE 3.8-US System Manual page 23

Hide thumbs Also See for ENERGY SYSTEM with SUNNY BOY STORAGE 3.8-US:
Table of Contents

Advertisement

SMA Solar Technology AG
7. Enter the name of the power profile in the field Name of the power profile.
8. Select the entry Peak Load Shaving from the drop-down list Operating mode of the
power profile.
9. Enter the target feed-in power in the field Limiting value for the grid feed-in. When this
value is reached, charging of the battery with the surplus energy starts.
10. Enter the target purchased power in the field Limiting value for the purchased energy
(from the utility grid). When this value is reached, discharging of the battery starts.
11. Make the time range setting. You can select on which days of the week, in which date range
and at what time the power profile should be valid. Even a power profile independent of the
days of the week, which should be valid on a set date, can be configured. For this, you must
select the the option Independent of days of the week.
12. To temporarily save the power profile and to possibly create other power profiles, select the
'save' icon to the right of the overview Created power profiles. The data are saved
temporarily on this page. The data are only transferred when the page is closed by clicking on
the [Save] button.
13. To assign priority to multiple power profiles, select the desired power profile in the overview
Created power profiles and set the priority by moving the power profile up or down.
14. To save the power profile and to close the page, select [Save].
15. To deactivate a power profile, select the desired power profile in the overview Created
power profiles and then select the entry Inactive from the drop-down list Operating mode
of the power profile.
6.4
Registering System in Sunny Portal
1. Register system in Sunny Portal: https://www.sunnyportal.com/Register
2. Carry out the system setup assistant.
3. To use Sunny Places, select Release system for Sunny Places in the extended system
properties.
4. Activate Smart Connected. To do this, select Yes, I would like to participate in the Smart
Connected program with this performance description. in the extended system
properties.
System Manual
6 Commissioning
SBSUL9540-SH-en-10
23