Connecting The Redundant Ac-Power Switch To The Site Power; Positioning The Clips; Positioned In Rack - IBM 2145-8F2 Hardware Installation Manual

System storage san volume controller
Hide thumbs Also See for 2145-8F2:
Table of Contents

Advertisement

Figure 25. Positioning the clips
3. Position the redundant ac-power switch in the rack first, pushing the cables
Figure 26. Positioned in rack

Connecting the redundant ac-power switch to the site power

You must connect the redundant ac-power switch to the site power before you test
the redundant ac-power switch.
Perform the following steps to connect the redundant ac-power switch to the site
power:
1. Determine a suitable cable route from the redundant ac-power switch to the
2. Route the main input-power cable of the redundant ac-power switch to the
3. Route the backup input-power cable of the redundant ac-power switch to the
4. Verify that the redundant ac-power switch power cables are tidy. Ensure that
34
IBM System Storage SAN Volume Controller: Models 2145-8F2 and 2145-8F4 Hardware Installation Guide
through to the front of the rack. Mount in place, as shown in Figure 26, using
the four M6 screws.
power distribution units.
specified power distribution unit, and connect it.
specified power distribution unit, and connect it.
they do not obstruct other equipment and that they are tied in place where
necessary.