GENERAL INFORMATION
About Engineering and Application Practices
This bulletin only refers to the assembly of the unit. To ensure a proper operation, a correct integration of the unit in
the overall installation is mandatory. For good engineering and application practices on layout, levelling,
connecting pipework, etc., please refer to our website: http://www.baltimoreaircoil.eu/knowledge-
center/application-information.
Shipping
BAC equipment is factory assembled to assure uniform quality and minimum field assembly.
The adiabatic pre-cooler sections of the TrilliumSeries equipment are shipped separately. Refer to below table for
number of adiabatic pre-cooler sections per model.
Model
DCV-S9122-*
DCV-S9123-*
DCV-S9124-*
DCV-S9125-*
DCV-S9126-*
Inspection Before Rigging
When the unit is delivered to the jobsite, it should be checked thoroughly to ensure all required items have been
received and are free of any shipping damage prior to signing the bill of lading.
The following parts should be inspected:
-
Exterior panels and covers
-
Fans
-
Heat Exchanger
-
Adiabatic Pre-Cooler Sections
4
W W W . B A L T I M O R E A I R C O I L . E U
Number of Fans
4
6
8
10
12
Number of Fans and Pre-Cooler Sections per model
Number of Adiabatic
Pre-Cooler Sections
2
2
4
4
4
1 General Information