START-UP AND COMMISSIONING

DCV Condensers - General

ROTATION OF FANS
Fans must rotate without obstruction and must rotate in the correct direction, which is indicated by arrows on the
equipment.
MOTOR VOLTAGE AND CURRENT
Check the voltage and the current of all three legs of the fan motors. The current should not exceed the nameplate
rating. After prolonged shutdown the motor insulation should be checked with a megger insulation tester prior to
restarting.
The voltage must not fluctuate more than +/-10% and the imbalance between phases must not be greater than +/-
2%.
UNUSUAL NOISE AND VIBRATIONS
Unusual noise and/or vibration are the result of malfunctioning of mechanical components or operational problems.
If this occurs, a thorough inspection of the entire unit followed by immediate corrective action is needed. If
required, consult your local BAC Balticare representative for assistance.
PURGE REQUIREMENTS
The installer of BAC condensers and closed circuit cooling towers must provide a proper system purging, which
enables purging air from the coils prior to operation. Entrained air can obstruct free drainage of cooling medium and
reduce thermal capacity. All connections (installed by others) must be leak free and tested accordingly. To verify
absence of non condensables in the refrigeration system, follow the instructions in the BAC Application Handbook
– EU Edition (http://www.baltimoreaircoil.eu/sites/BAC/files/BAC_Application_Handbook_EU-EDV.pdf), section
"Condenser Engineering Guidelines" on page 51.
5 Start-up and Commissioning
5 Start-up and Commissioning