Rigging; Unloading Of Equipment - BAC DCV Series Rigging And Installation Instructions

Table of Contents

Advertisement

DCV
DCV-AD
3

RIGGING

Unloading of Equipment

1. The equipment arrives on site by truck.
It is recommended to unload the unit with a crane. The Adiabatic Pre-Cooling Sections for the TrilliumSeries
are crated separately. A forklift should be used for unloading of the crate with Adiabatic Pre-Coolers.
A crane must always be used to unload the unit from the truck. Do not attempt to unload the unit using a forklift.
2. Spreader bars of the full width of the section must be used between the lifting cables to prevent damage to the
section.
3. For extended lifts or where hazards exist, it is recommended to use the lifting devices in conjunction with
safety slings placed under the unit.
4. For each unit, only one lift is required. Lifting ears are foreseen on each unit.
5. Attach the lifting devices to the unit at the four corners as per rigging methods below. Do not use lifting hooks to
lift the unit, use shackles as shown on below picture. Unload the unit from the truck.
BEFORE AN ACTUAL LIFT IS UNDERTAKEN, ENSURE NO WATER, SNOW, ICE OR DEBRIS
HAS COLLECTED IN THE UNIT. SUCH ACCUMULATIONS WILL ADD SUBSTANTIALLY TO THE
Use shackles to lift the unit
6. Install the unit in its final position and anchor to the support beams (supplied by others).
10