Document No. 997-1002
Installation Instructions
February 12, 2009

2. General Installation Requirements

For proper installation and subsequent operation of each
controller,
pay
special
recommendations:
-
It is recommended that the controller(s) be kept at room
temperature for at least 24 hours before installation to
allow any condensation that may have accumulated, due
to low temperature during shipping or storage, to
evaporate.
-
Upon unpacking the product, inspect the contents of the
carton for shipping damages. Do not install damaged
controllers.
-
Allow for proper clearance of controller enclosure, wiring
terminals and service pin for easy access, hardware
configuration and maintenance. Remember to record the
®
Neuron
ID located on both sides of the controller (in text
and barcode format) for later commissioning.
-
The controller is designed to operate under the following
environmental conditions:
Ambient temperature from 32°F to 122°F (0°C to 50°C)
Relative humidity from 0% to 90%, non-condensing.
-
Ensure proper ventilation for the controller and avoid
areas where corroding, deteriorating or explosive vapors,
fumes or gases may be present. The controller must be
oriented with the ventilation slots and power supply/output
terminal block connector towards the top, for safety and to
permit proper heat dissipation.
-
The plastic enclosure has a back plate that is separable
from the front plate, allowing the back plate (with the
connectors) to be shipped directly to the installation site
while all the engineering is done in the office.
-
If the controller is used and/or installed in a manner not
specified, the functionality and the protection provided by
the controller may be impaired.
Any type of modification to any SLX Series product
will void the product's warranty.
Take special care to keep the front and back plate
aligned when separating and joining them.
Take
reasonable
electrostatic discharges to the controller when
installing, servicing or operating the controller.
Discharge
accumulated
touching your hand to a securely grounded object
before working with this controller.
3. Controller Markings (Symbols)
Certain markings (symbols) can be found on the back plate of
the controller and are defined as:
HIGH VOLTAGE Symbol: Direct contact will cause
electrical shock or burn.
Warning Symbol: Significant information required.
Refer to Hardware Installation Guide.
Double Insulation Symbol: These controllers are
built with double insulation.
Page 2 of 8
attention
to
the
following
precautions
to
prevent
static
electricity

4. General Wiring Recommendations

Due to HIGH VOLTAGE, direct contact will
cause electrical shock or burn. Turn off power
before any kind of servicing.
It is recommended to use a 2-line main power
disconnect to be located near the controller (the
minimum power requirements: 300VAC, 20A).
Minimum cable temperature rating of all cables
must be 80°C.
-
All wiring must comply with electrical wiring diagrams as
well as national and local electrical codes.
-
To connect the wiring to the controller, use the terminal
connectors. It is recommended to remove the front plate
from the back plate to facilitate the wiring process;
however, it is possible to do all wiring with the front and
back plates together. Use a small flat screwdriver to
tighten the terminal connector screws after the wires are
inserted.
-
Power type cables (i.e. for power, 2- and 3-wire voltage
and current inputs and outputs, as well as relay and triac
outputs) should be kept apart from other types of wiring for
safety and to avoid any ambient noise transmission to
other wires.
-
The board connectors accept wires or flat cables ranging
from 22 to 14AWG (0.644 to 1.630mm diameter) per pole.
However, power cables must remain between 18 and
14AWG (1.024 to 1.630mm diameter).
-
Do not connect the universal inputs, analog outputs or
common terminals to earth or chassis ground (unless
stated otherwise).
-
Keep all wires away from high speed data transmission
cables (ie. Ethernet, etc.).
-
Keep input and output wiring in conduits or trays, or close
to the building frame if possible.

5. Mounting Instructions

Each controller can be mounted on a DIN rail to speed up the
installation process. The controllers are also equipped with two
mounting holes of 0.25" (6.35mm) by 0.165" (4.191mm). They
can be mounted in a panel or on a wall by using appropriate
screw types (use sheet metal, thread forming or self-tapping
by
screws accordingly).
Do not mount the controller on a flat surface where
the front plate would be facing up. It must be
mounted on a vertical surface such as a wall.
DIN Rail-Mounted Installation
1. Make sure that the DIN rail is properly mounted on the wall.
2. Simply clip controller onto the DIN rail.
Wall-Mounted Installation
1. Open the controller by separating the front and back plate
using the side clips.
2. From within the back plate use the mounting holes to mark
the location of any holes that need to be drilled.