3
INSTALLATION
3.1
Unloading/site transport
Important:
All transport should take place with the chiller in hori-
zontal position.
3.1.1
Handling with truck
Warning
High centre of gravity! Lift the chiller carefully.
6
www.swegon.com
3.1.2
Handling with crane
Place two line spreaders on top of the chiller and two on
the underside of the pallet or below the chiller and lift in
the pallet (or the chiller if the pallet is not to be included).
See the illustration.
3.2
Arrangement
Place the COOL DX at a suitable location.
Safety isolating switch/main switch must have the requi-
site space to serve according to applicable electrical regu-
lations.
The unit can stand with the back against the wall, but to
facilitate any service of the rear compressor, a distance of
about 1 metre is recommended.
We reserve the right to alter specifications.
GB.COOLDX.SI.G.190603