New Construction Installation
1. Mount Speed Spring Brackets and Stationary Brackets to each
side of sign box. (Mount bracket base parrallel to the direction
of your raceway)
4. Verify all LEDs of light bars point to sign face.
7. Mount power supply
• Identify input and output secondary wires. Connect the
power unit to the supply in accordance with the applicable
local, state, and country electrical codes, and the
instructions found in the power supply installation guide.
All power supplies must be installed in a raceway or suitable
electrical enclosure.
• If required, the disconnect switch shall be installed by
qualified personnel, in accordance with applicable local,
state, and country electrical codes.
• Spacing between LED power supplies shall be at least
25.4 mm (1 in) from end to end and 101.6 mm (4 in) from
side to side, in accordance with UL 48 Par. 4.2.3.2.3.1
2. lnsert Light bars onto Speed Spring Brackets first.
5. Connections: Wire the Concorde Bar II with male and female
connectors to make longer cascade. (see Cascading
Information Guidelines on page 7 to see how many bars can
be run in a series)
8. Connect to power supply: Connect the white output wire to
the red Concorde cable wire and the black output wire to the
black cable wire. Connect female cable end to male end
coming off of Concorde lamp and tighten collar.
Installation Guide | www.hanleyledsolutions.com | 800.542.9941
3. Push the Concorde Bar II down onto the Speed Spring Bracket,
then insert other end onto stationary bracket.
6. Unused wire ports should be capped with Watertight End
Cap provided in box, or use another extension cable to tie
the port back to the power supply.
9. Make sure all wire connections are ready and correct.