This document is valid in United Kingdom and Ireland from June 2019 onwards. It remains subject to change. When carrying out the installation and operation of the Q.FLAT-G5 flat roof system, the data sheets and other information published by the manufacturer at the time of purchase of the system or the components shall be considered valid unless the purchaser or operator is informed of more up-to-date requirements.
For further information, please visit our website at www.q-cells.com. INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
Q.PEAK DUO-G5), including frame. • The latest version of the product data sheet is always decisive. INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
120-half-cell solar modules (e.g. Q.PEAK DUO-G5) 20005103 Steel + stainless Q.FLAT-G5 end clamp with screw steel + plastic INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
Ground profile folded out Ballast carrier Ballast carrier DUO Ground profile connector End clamp INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
All steps in a system design Ä Plan the Q.FLAT-G5 with less than 1.5 m distance to the roof their end faces abutted to the spacer. This results in a layout grid can be completed with just one program. Snow and wind load edge.
DANGER! Danger to life due to electric shock! WARNING! Risk of injury due to falling modules! Besides the project report, tools and aids that are not included in the scope of supply are required for installation of the Q.FLAT-G5. Ä...
ASSEMBLY ASSEMBLY 4.1 PREPARATIONS FOR ASSEMBLY 4.2 PERFORMING THE ASSEMBLY The distribution of the ballast weights specified in the ballast plan created by Q CELLS must be strictly observed. The following Ä Clean roofs and remove obstructions. Ä Fold up the middle support column and pull standard ballast elements made of concrete are recommended for the ballast: Ä...
Page 10
Aids, tools: Project report, layout plan purpose. • Integration in a lightning protection system is also possible. wide slim INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
B. Ä Use ballast carrier position B. Aids, tools: Layout plan, ballast plan INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
Only connect cables with plugs. modules must be de-energised. in proper, safe condition. Switch off the inverter. INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
(see p. 26, work steps 1 and 2). Ä The terminals clamps function as edge and centre terminals. Klick INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
Do not allow isopropanol to run between the module and frame or into the module's edges. INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...
Prof. Dr.-Ing. H. Ruscheweyh: “Wind tunnel test for the Q.CELLS flat roof system”, RC Ruscheweyh Consult INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS INSTALLATION AND OPERATION MANUAL FOR FLAT ROOF SYSTEM Q.FLAT-G5 – Q CELLS...