J. Transfer Switch Operation
a. Automatic Sequence of Operation
Note: Time delays indicated below are factory default settings only. Refer to Owners manual for alternate time delay settings available on TSC 9
Controller
UTILITY POWER FAIL
When voltage drops on any phase of the utility supply below 70% of rated voltage, a generator start sequence will be
initiated
GEN START
The generator will start following expiry of the 3 second Gen Start timer
GEN WARM-UP
A generator warm-up period will be initiated once the generator starts and reaches 80% rated voltage and 90% rated
frequency
TRANSFER TO GEN
The load will transfer to the generator supply following expiry of the 10 second Gen Warm-up timer
LOAD SHED ACTIVATE
All non-essential loads connected to Load Shed control circuit will be de-energized once the generator transfers on load
provided the Load Shed feature has been enabled. Refer to Owners manual for further details.
UTILITY POWER
When utility power is restored to above 80% rated voltage on all phases, a utility return timer sequence will be initiated
RETURN
TRANSFER TO UTILITY
The load will transfer from generator to utility power following expiry of the 120 second utility return timer provided both
generator and utility voltages are in-phase at time of transfer.
LOAD SHED RESET
All non-essential loads connected to Load Shed control circuit will be re-energized once load transfers to utility power.
GEN COOLDOWN
The generator will automatically stop following expiry of the 2 minute cool down timer.
b. TSC 9 Controller Operation Pushbuttons
TEST
To Load Test, press and hold the "T" pushbutton for 2 seconds until LED light above pushbutton comes ON. The generator
will start and transfer on load per Automatic Sequence.
To cancel Load Test, press and hold the "T" pushbutton for 2 seconds until LED light above pushbutton goes OFF. The
load will re-transfer back to the utility power per Automatic Sequence.
EXERCISE
To set Exercise mode and schedule, press and hold the "E" pushbutton for 2 seconds until LED light above pushbutton
starts flashing. The generator will start and operate off load (or ON Load if selected). The generator will operate for 30
minutes then will automatically stop. Exercise LED will change from flashing to continuously ON, indicating exercise clock
schedule is enabled. The generator will automatically start and exercise in 7, 14 or 28 day cycles as selected.
To cancel Exercise, press and hold the "E" pushbutton for 2 seconds until LED light above pushbutton goes OFF.
TIMER BYPASS
TIMER BYPASS: Press and hold the "E" and "T" pushbutton together for 2 seconds to bypass any active time delay.
LAMP TEST
ALARM RESET
LAMP TEST: Press and hold the "E" and "T" pushbutton together for 5 seconds to activate lamp test function.
ALARM RESET: Press and hold the "E" and "T" pushbutton together for 10 seconds until alarm LED goes out.
THOMSON POWER SYSTEMS • 9087A - 198th STREET, LANGLEY, BC CANADA V1M 3B1
TELEPHONE: (604) 888-0110 • FAX: (604) 888-3381 • E-MAIL: info@thomsonps.com • www.thomsonps.com
Part ID

Advertisement

Table of Contents
loading

Table of Contents