1MRS240044-IB A
4.8.2
REF615R
Engineering Manual
GUID-2C50CFC5-0C7E-495C-B9C9-4EE66C3E5D23 V1 EN
Figure 24:
PCM600: IEC 61850 signal designation concept
The created technical key for the full path name of the IED would be: AA1J1Q01A1.
•
AA1 = substation in the project
•
J1 = voltage level from 20 to 30 kV
•
Q01 = the first bay in the voltage level
•
A1 = first IED in the bay Q01
Setting the technical key
1.
In the Plant Structure view, right-click the IED and select Set Technical Key in
IED.
2.
From the list that opens, select Set Technical Key in IED.
Section 4
Setting up a project
49