Workflow

Save the work
between the
different steps
DNP3
Modbus
Signal engineering
GUID-D928ED86-61A8-45D4-A472-4E31727F4315 V1 EN
Figure 3:
IED engineering workflow proposal based on practical experience and
dependencies of the steps
It is possible to make a different kind of a sequence based on the information available
at the time when the project is started. This means that several iterations may be
needed to complete the project.
Start
Create plant structure and
insert IED objects
Project
ACT
Configure IED functionality
SMT
Parametrization
PST
Create single line diagram
for local HMI
GDE
IEC 61850
Export
SCD
IEC 61850
CMT
Configuration
ACT
or IET600
Import
SCD
SMT
IED
Write configuration to IED
WRITE
End
Section 2
IED engineering process
Export SCL files from
PCM600
Import SCL files to IEC 61850
Configuration or IET600 and do
signal engineering. Export
updated SCL files from IEC
61850 Configuration or IET600.
Import SCL files to PCM600
Make GOOSE connections