UniGear ZS3.2
29.3
e) Spring resilience checking: press the contact spring 29.3 down for
around 10 mm, the contact spring 29.3 should be rebounded freely
after loosen. Please repeat above process for 3 times.
3
Busbar
29.3 Contact spring
f) Finally using multimeter to check the contact resistance between
busbar 3 and metal tube 29.4 of busbar bushing 29. The contact
resistance must be less than 5 ohm. Please recheck the installation
correctness from step a) to step e) if thecontact resistance greater
than 5 ohm until it meet the test requirement.
3
Busbar
29
Busbar bushing
29.3 Contact spring
29.4 Metal tube
I N S T R U C T I O N M A N U A L
3
29.3
29.4
29
3