Integral Solenoid - Saunders M-VUE Installation, Operation And Maintenance Manual

Intelligent sensing technology
Table of Contents

Advertisement

Calibration

Integral Solenoid

Forcing the Integral Solenoid
1.
To energize solenoid valve, hold the magnetic key over
H1 for 3 secs. This will operate the actuator.
2.
To de-energize the solenoid hold the magnetic key over
H1 for 3 sec. The actuator moves to the fail-safe position
Self Calibration (Integral Solenoid)
Note: this guide only details self-calibration process for a
sensor with integral solenoid at the sensor.
For calibration via a network, please refer to the
corresponding network section of this manual.
1.
Hold the magnetic key over H2 for 6 seconds. The P1
LED indicator will turn green. M-VUE will automatically
perform a self-calibration routine. It will automatically
open and close 3 times.
2.
If the self calibration routine is successful all the LEDs
will flash green for 2 seconds and M-VUE will return to
normal run mode
3.
If the self calibration routine fails all LEDs will flash
red for 2 seconds. P1 will remain flashing waiting for
confirmation to try another calibration.
Note: If the calibration fails, the last successful calibration will
remain stored at the sensor.
www.cranecpe.com
6 s to confirm Self Calibration
Crane ChemPharma & Energy
13

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the M-VUE and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents