Wiring

WARNING
Electric shocks can be fatal! Before working on
possible live components, ensure the unit is discon-
nected from the power supply.
▷ The solenoid actuator heats up during operation
depending on ambient temperature and voltage.
> +80 °C
▷ The rectifier adapter must be installed.
▷ Use temperature-resistant cable (> 80°C).
 Disconnect the system from the electrical power
supply.
2 Shut off the gas supply.
▷ Wiring to EN 60204-1.
▷ The actuator can be rotated.
3
4
6
7
1 = N
2 = L
2
▷ Plug insert can be rotated in 90° steps.
9
10
12
5
8
3
1
11

Tightness test

CAUTION
Please observe the following to ensure that the VGP
is not damaged during the tightness test:
Check max. inlet pressure – see type label.
Test pressure ≤ 1.5 x max. inlet pressure.
 Close the solenoid valve.
2 To be able to check the tightness, shut off the
downstream pipeline as close as possible to the
valve.
3
≤ 1,5 x p
N
2
0
4 Open the solenoid valve.
5
N
2
≤ 1,5 x p
6 Tightness OK: the unit is ready for operation.
7 Open the pipeline again and release the gas
supply.
▷ VGP leaking: dismantle the unit and return it to
the manufacturer.
GB-3