RECOMMENDED SEQUENCE WHEN
INSTALLING SPM
Different situations require different installation sequences. The
possibilities are myriad and each scenario cannot be discussed
in this manual. Should you have anything other than a standard
installation, it is strongly recommended you contact Weir Oil & Gas
Engineering before proceeding. A standard installation sequence
is as follows:
FIRST
Install SPM
FSR Anchor Crossover Assemblies within the flow
®
line where applicable. See page 27 for more information. This is
critical because they require installation into the flow line. If these
are not included, the flow line must be disassembled and these
components installed at a later point.
NOTE: Anchor Crossovers may be included at various points
in the flow-line to allow disassembly of a smaller section
of the SPM
necessary in order to replace internal components.
SECOND
Install the SPM
more information.
TIP - It is most efficient to have one person lay out all the
SPM
FSR Ribs at appropriate locations along the flow line
®
prior to installing them.
TIP - It is recommended that one person lift the flow
line with the pipe jack (or similar leverage) while another
individual installs the Rib at each wing union connection.
FSR to access the flow iron. This may be
®
FSR Ribs next. See pages 14-17 of this guide for
®