Test Running - Friedrich M12CJ Installation Manual

Ductless split systems
Hide thumbs Also See for M12CJ:
Table of Contents

Advertisement

Test Running

- Check that all tubing and wiring are properly
connected.
- Check that the gas and liquid side service
valves are fully open.
Prepare remote controller
1
Remove the battery cover by pulling it ac-
cording to the arrow direction.
2
Insert new batteries making sure that the
(+) and (–) of battery are installed correctly.
3
Reattach the cover by pushing it back into
position.
!
NOTE
- Use 2 AAA(1.5volt) batteries. Do not use
rechargeable batteries.
- Remove the batteries from the remote
controller if the system is not used for a
long time
Anchoring of outdoor unit
- Fix the outdoor unit with a bolt and
nut(ø10mm).
- When installing on the wall, roof or rooftop,
anchor the mounting base securely with a
nail or wire assuming the influence of wind
and earthquake.
- If the vibration of the unit is transmitted to the
pipe, secure the unit with an anti-vibration
rubber.
Bolt
Evaluation of the performance
Operate the unit for 15~20 minutes, then
check the system refrigerant charge:
- Measure the pressure of the gas side service valve.
- Measure the air temperature from inlet and
outlet of air conditiioner.
- Ensure the difference between the inlet and
outlet temperature is more than 45°F.
- For reference; the gas side pressure at opti-
mum condition is shown on table (cooling)
The air conditioner is now ready to use.
Inlet temperature
Discharge air
Outside
Refrigerant
ambient TEMP.
R-410A
95°F
*The feature can be changed according to a type
of model.
23
Tubing connection
Discharge
temperature
The pressure of
the gas side
8.5~9.5kg/cm
2
G
(120~135 P.S.I.G.)