WARNING
Opening device in energized state
Danger of explosion in areas subject to explosion hazard.
● Only open the device in a de-energized state.
● Check prior to commissioning that the cover, cover locks, and cable inlets are assembled in accordance with the
directives.
Exception: Devices having the type of protection "Intrinsic safety Ex i" may also be opened in energized state in hazardous
areas.
Note
Hot surfaces
Hot process medium and high ambient temperatures lead to hot surfaces which can cause burns.
● Take corresponding protective measures, for example wear protective gloves.
5.2

Introduction to commissioning

Following commissioning, the transmitter is immediately ready for use.
To obtain stable measured values, the transmitter needs to be allowed to warm up for five minutes or so after the power
supply is switched on. Upon switch-on, the transmitter goes through an initialization routine (display at the end: "Init done").
If the transmitter initialization routine does not complete, check the auxiliary power.
The operating data must correspond to the values specified on the nameplate. If you switch on the auxiliary power, the
transmitter will operate.
The following commissioning cases are typical examples. Configurations different from those listed here may be meaningful
depending on the system configuration.
24
SITRANS P DS III (7MF4.33.. 7MF4.34.. 7MF4.35..)
A5E03434626-03, 06/2013

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

7mf4.34 series7mf4.33 series7mf4.35 series

Table of Contents