NOTE: De-energize the compressors before taking any test
measurements to assure a dry evaporator coil.
4.
The CFM through the unit can be determined from the
pressure drop indicated by the manometer by referring to
Figure 28. In order to obtain an accurate measurement, be
certain that the air filters are clean.
5.
To adjust Measured CFM to Required CFM, see SUPPLY
AIR DRIVE ADJUSTMENT.
6.
After readings have been obtained, remove the tubes and
replace the dot plugs.
7.
Tighten blower pulley and motor sheave set screws after
any adjustments. Re-check set screws after 10-12 hrs. run
time is recommended.
Failure to properly adjust the total system air quantity
can result in extensive blower damage.
Method Two
1.
Drill two 5/16 inch holes, one in the return air duct as close
to the inlet of the unit as possible, and another in the supply
air duct as close to the outlet of the unit as possible.
2.
Using the whole drilled in step 1, insert eight inches of 1/4
inch metal tubing into the airflow of the return and supply
air ducts of the unit.
NOTE: The tubes must be inserted and held in position
perpendicular to the airflow so that velocity pressure
will not affect the static pressure readings.
Figure 28: Dry Coil Delta P
42
2650
2450
2250
2050
1850
1650
1450
037
1250
1050
850
0
0.02
Dry Coil Delta P (IWG)
3.
Use an Inclined Manometer or Magnehelic to determine
the pressure drop across the unit. This is the External
Static Pressure (ESP). In order to obtain an accurate
measurement, be certain that the air filters are clean.
4.
Determine the number of turns the variable motor sheave
is open.
5.
Select the correct blower performance table for the unit
from Tables 17 and 18. Tables are presented for side and
downflow configuration.
6.
Determine the unit Measured CFM from the Blower
Performance Table, External Static Pressure and the
number of turns the variable motor sheave is open.
7.
To adjust Measured CFM to Required CFM, see SUPPLY
AIR DRIVE ADJUSTMENT.
8.
After reading has been obtained, remove the tubes and
seal holes.
9.
Tighten blower pulley and motor sheave set screws after
any adjustments. Re-check set screws after 10-12 hrs. run
time is recommended.
NOTE: With the addition of field installed accessories repeat
this procedure.
Failure to properly adjust the total system air quantity
can result in extensive blower damage.
049, 061
0.04
0.06
0.08
0.1
0.12
Johnson Controls Ducted Systems

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents