32 | Test Run
9.
Test Run
Before Test Run
Only perform test run after you have completed the following steps:
• Electrical Safety Checks – Confirm that the unit's electrical system
is safe and operating properly
• Gas Leak Checks – Check all flare nut connections and confirm that
the system is not leaking
• Confirm that gas and liquid (high and low pressure) valves are fully
open
Test Run Instructions
You should perform the Test Run for at least 30
1. Connect power to the unit.
2. Press the ON/OFF button on the remote controller to turn it on.
3. Press the MODE button to scroll through the
COOL – Select lowest possible temperature
•
HEAT – Select highest possible temperature
•
4. Let each function run for 30 minutes, and perform the following
checks:
6 720 869 159 (2016/12)
List of Checks to Perform
No electrical leakage
Unit is properly grounded
All electrical terminals properly covered
Indoor and outdoor units are solidly
installed
All pipe connection points do not leak
Water drains properly from drain hose
All piping is properly insulated
Unit performs COOL function properly
Unit performs HEAT function properly
Indoor unit louvers rotate properly
Indoor unit responds to remote controller
PASS/FAIL
Outdoor (2):
Indoor (2):
Installation Manual