Starting The Self-Test (For Italy Only); Activating The Receipt Of Control Signals (Only For Italy) - SMA SUNNY BOY 1.5 Operating Manual

Hide thumbs Also See for SUNNY BOY 1.5:
Table of Contents

Advertisement

9 Configuration
3. On the right-hand side of the menu bar, select the menu User Settings (see Section 8.2
"Design of the Inverter User Interface", page 37).
4. In the subsequent context menu, select [Start the installation assistant].
☑ The installation assistant dialog opens.
9.3

Starting the Self-Test (For Italy Only)

The self-test is only required for inverters to be commissioned in Italy. The Italian standard requires
that all inverters feeding into the utility grid are equipped with a self-test function in accordance with
CEI 0-21. During the self-test, the inverter will consecutively check the reaction times for
overvoltage, undervoltage, maximum frequency and minimum frequency.
The self-test changes the upper and lower disconnection values for each protective function on a
linear basis for frequency monitoring and voltage monitoring. As soon as the measured value
exceeds the permitted disconnection threshold, the inverter disconnects from the utility grid. In this
way, the inverter determines the reaction time and checks itself.
After the self-test has been completed, the inverter automatically switches back to feed-in operation,
resets the original disconnection conditions and connects to the utility grid. The test takes
approximately three minutes.
Requirements:
☐ The country data set of the inverter must be set to CEI 0-21 internal.
Procedure:
1. Call up the inverter user interface (see Section 8.1, page 34).
2. Log in as Installer.
3. Select the menu System Configuration.
4. Select [Settings].
☑ A context menu opens.
5. Select [Start self-test] in the context menu.
6. Observe the instructions shown in the dialog and save the report of the self-test, if necessary.
9.4
Activating the Receipt of Control Signals (Only for
Italy)
In order for PV systems in Italy to receive control commands from the grid operator, set the
following parameters. Some function-sensitive parameters can only be viewed by qualified persons
and can only be changed by qualified persons.
42
SB15-25-BE-en-10
SMA Solar Technology AG
Operating Manual