Do's & Don'ts
DO:
• Install a bypass line around the meter
• Clean the filter on a regular basis
• Purge air from the meter before operating your system
(Flowing near the meters maximum flow rate for a
given viscosity will purge air bubbles. Tilting, tapping
or shaking the meter at lower flow rates will also
dislodge entrapped air)

Piping Diagram

Horizontal Installation
FLOW
VALVE 1
FILTER
Horizontal Two-Way Flow
VALVE 1
FILTER
Max Machinery, Inc. G-Series User Manual
FLOW METER
VALVE 2
VALVE 3
BYPASS
FLOW
FLOW METER
VALVE 2
FILTER
VALVE 3
BYPASS
© Copyright 2018
DON'T:
Run water or aqueous solutions through the meter
(except the 234 Series of meters)
Put steam or compressed air through the meter.
(Air may over-speed and damage the meter)
Disassemble the meter
Apply excessive differential pressure across the meter
Exceed the maximum flow rates or pressure ratings
for your meter
Let materials solidify in the meter
Try to pump through the meter if it contains frozen
material. Re-melt the material completely before
trying to pump through the flow meter.
Vertical Installation
FLOW
Rev2018A
VALVE 2
FLOW METER
VALVE 3
BYPASS
FILTER
VALVE 1
8