Dell Force10 E300 Quick Start Manual page 12

Hide thumbs Also See for Force10 E300:
Table of Contents

Advertisement

E1200i TeraScale and ExaScale AC Chassis Ground
Step
Task
Locate the chassis ground connector nuts on the rear of the chassis.
1
Install the grounding cables to the ground nuts. The grounding cable
2
must comply with your local electrical codes in size and color (typically
the color is green or green with yellow stripe).
listed 2-hole lug with 1/4-inch holes on 3/4-inch spacing.
Cable Connector Required for E1200i AC
High-strand-count
All measurements in inches.
Use ANSI UNC 1/4-20 x 12 bolt.
3
Tighten the bolt (torque should not exceed 25 inch/lbs).
4
Connect the opposite end of the grounding cable to the nearest
5
appropriate facility grounding post.
E1200i TeraScale and ExaScale DC Chassis Ground
Step
Task
Remove one outer nut and one washer from each of the six studs. One
1
nut should remain, tight on the stud. If the inner nut is loose, re-tighten it
to 25 inch/lbs, maximum.
Locate the chassis ground connector studs on the PEM front panel. The
2
two rightmost studs are the ground connection.
10
Installing the Hardware
NOTE:
Grounding cables must be terminated only with a UL-
conductor
0.267
diameter
2 Holes
0.750"