Wolf COB Technical Manual And Installation Instructions page 53

Oil condensing boiler for central heating
Table of Contents

Advertisement

C) Checking the CO
adjustment
2
Completing the adjustments
3062547_201802
33 CO
check/adjustment via pump
2
pressure
- After completing the work, refit the casing cover and check the CO
boiler closed.
- When correctly set, the boiler should not exceed the maximum CO
accordance with the table below.
Appliance closed
Stage 2
CO
max
2
Stage 1
Stage 2
O
min.
2
Stage 1
- If the CO
value increases too greatly, the balanced flue must be checked.
2
- Enter flue gas values such as CO
commissioning report (see the commissioning report chapter).
- Remove the test probe and close the test port. Ensure the cap is seated firmly.
- Check the control parameters and match them to the system if necessary.
- Check the condensate drain.
- Instruct the customer in the operation of the device, with the aid of the operating
and installation instructions.
- Complete the commissioning report (see the commissioning report chapter) and
hand over the instructions to the customer.
- Instruct the customer about the need for annual servicing.
- Instruct the customer about energy saving options.
- Refer your customer to section "Information regarding energy efficient operation" in
the operating instructions.
COB-15
COB-20
13,5 %
13,5 %
2,7 %
2,7 %
content, flue gas CO content and soot value in the
2
value with the
2
values in
2
COB-29
COB-40
53