B. Manufacturer's representative to verify proper and complete installation.
3.2
START-UP
A. Shall be performed by Raypak factory-trained personnel.
B. Test during operation and adjust if necessary:
1. Safeties (2.2 - F)
2. Operating Controls (2.3)
3. Static and full load gas supply pressure
4. Gas manifold and blower air pressure
C. Submit copy of start-up report to Architect and Engineer.
3.3
TRAINING
A. Provide factory-authorized service representative to train maintenance personnel on procedures
and schedules related to start-up, shut-down, trouble shooting, servicing, and preventive
maintenance.
B. Schedule training at least seven days in advance.
Project Name / Date
END OF SECTION