Sealed Systems; Electrical Connections; Pre-Commissioning; Gas Supply - Hamworthy UF150-1 Installation, Commissioning And Operating Instructions

Upton series. floor standing, condensing , open flue, fully modulating, pre-mix, gas fired boilers for heating & domestic hot water installations
Table of Contents

Advertisement

5.4 Sealed Systems

Boilers must not be capable of isolation from the safety valve. Valves between boiler and safety valve to be three
way type such that when boiler is isolated from the safety valve it is open to atmosphere. Hamworthy Heating Ltd
recommend using the safety valve connection provided on the boiler.
Where using Hamworthy Heating Ltd pipework kits, assembly of these is detailed in Operation and Maintenance
manual supplied with kit.

5.5 Electrical Connections:

The following electrical connections are provided on each module.
Supply: Live, Neutral and Earth. See Section 4.5 for details.
Optional Boiler Fault Alarm & Normal Run Signal Output (optional AGU clip-in kit)
0-10v Analogue Control Signal Input
Remote on/off Control Input
Boiler Pump Output, DHW pump output, motorised valve output
Safety Interlock Circuit Input
Optional LPB Bus for use with Merley cascade control (optional OCI clip-in kit) & Master/Slave sequencing

6.0 PRE-COMMISSIONING

The following pre-commissioning check must be carried out before the boiler is commissioned.

6.1 Gas Supply.

Ensure that gas installation pipe work and meter has been soundness tested and purged to IGE/UP/1 or IGE/
UP/1A as appropriate. Test and purge certificates should be available for viewing.
6.2 Ventilation
Ensure that ventilation and air supply to plant room is correct.
6.3 Pipe work, Valves and Pump
Ensure that;
System flushing and suitable water treatment has been implemented
Pipe work and valve arrangement is installed to Hamworthy Heating recommendations.
Circulating system is full of water, vented and pressurised appropriately and the water quality checked.
Circulation pump is fitted, working and interlocked where required.
Pipe work connections to boiler are fitted correctly.
Safety valve is correctly sized and located.
All necessary isolation valves are open.
Condense connections on boiler and flue are connected and piped to drain.
Heat load is available.

6.4 Flue

Ensure that;
Flue system is correctly designed and installed to suit boilers.
Flue passages to chimney are clear.

6.5 Electrical

Ensure that;
Electrical connections are correct and isolatable.
External controls are operational.
WARNING: WHEN THE FRONT COVER IS REMOVED AND THE BOILER IS
OPERATIONAL, CARE MUST BE TAKEN WITH ELECTRICAL COMPONENTS AND
HAMWORTHY HEATING LTD
ACCESS TO PRIMARY INSULATION.
UPTON FLOOR STANDING SERIES
19
500001340/C

Hide quick links:

Advertisement

Table of Contents
loading