Concrete & Tile Flooring; Wall Panel & Door Section Installation - Kolpak Walk-In Installation & Operation Manual

Table of Contents

Advertisement

Gasses emitted by curing concrete floors or tile grout will damage panel finishes.
Adequate ventilation must be provided when the concrete floor or tile setting bed and
grout is curing. Leave all doors open for ventilation. If concrete or tile is to be installed
after walk-in is erected, protect the wall finish by applying a protective covering.
Review the wall panel and door sections layout on the assembly drawing. Panels are
labeled with numbers corresponding to those on the assembly drawing.
 Start with a back corner and work around the unit both ways, ending with a front
corner. Do not lock the walls into the floor/screed at this time.
 Begin wall panel assembly by cam-locking a back corner panel and one wall
panel together. See assembly drawing for correct panel placement, and tongue
and groove directions.
 Door sections will be installed in sequence along with wall panels. Use a level to
set the door section plumb and level.
www.kolpak.com
Concrete & Tile Flooring
CAUTION
Wall Panels & Door Section Installation
800-225-9916
15