Installation of overlay material is best accomplished before the refrigeration system has
been started, and before any product has been loaded. In the event that overlay must
be added at a later date, ensure that the refrigeration system has been turned off and
that the subsurface has been allowed to return to a normal working temperature.
Installing at a low temperature may not allow the adhesive/sealant to cure adequately.
 Clean and dry subsurface.
 Apply silicone to the underside of flooring overlay material.
 Begin laying first row of flooring overlay ½" away from the edge of the floor
according to the drawing and secure to the subsurface with sheet metals screws
or anchors.
 All sheets must be as flush as possible to one another.
 All sheets must be secured using a sheet metal screws or anchors every 24".
Ensure that at least one fastener is used near each corner of the overlay
material.
 Continue to follow the layout according to the drawing until all sheets are flush
and secured to the subsurface.
 Caulk all seams and edges of flooring overlay material.
 Allow 1-3 hours for the adhesive/sealant to dry prior to resuming use of the walk-
in.