19. MAINTENANCE

The maintenance operations must be carried out from:
The front of the boiler (main burner, electrodes, control panel, sight hole).
The back of the boiler (gas shut-off valve, air damper, fan motor).
This allows that several boilers can be installed in a modular way, one beside the other (leaving a distance of 3 cm
between them).
19.1 Procedure to dismantle the burner
Be sure that:
The boiler general switch is on the OFF position.
-
The gas duct to the boiler is closed.
-
Take out the frontal casing panel of the boiler and lift the top.
Once made these steps, you can place the control panel in two different positions, in order to allow the reading of
parameters when you are carrying out the boiler maintenance.
RANGE ADI CD 200 to 450:
Front view of the boiler without lower casing panel
Second position of the control panel