NLC‐100SH Installation and troubleshooting 
The reading will be prefixed with 'I' for Internal board, or a number for an 
expansion board: '1' for the first expansion board, '2' for the second and '3' 
for the third.
Running the "Electrical Test"
The NLC has a built‐in test that will activate each station in turn for just one 
second in order to check if they are responding correctly. The stations must 
be connected to the solenoids that activate valves in the landscape, and 
the test can tell whether the stations and solenoids are working correctly 
in conjunction.
1 Turn the dial to 
:
SOLENOID AMPS
AUTO
PAUSE/
STOP
MANUAL
SET DATE & TIME
RESUME
OFF
PROGRAM
RAIN OFF
RUN TIME
RAIN ALARM STATUS
WATER DAYS
VIEW ALARMS
START TIME
VIEW ET & RAIN
WATER BUDGET / ET
PROGRAM STATUS
VIEW MOISTURE SENSOR
ADVANCED
SETUP SENSORS
SOLENOID AMPS
Now the display will look like this: