When checking the cable connections of the eA360, check the items listed in Table 3-5 in
order.
Table 3-5 Cable connection check of the eA360
No.
1
2
Step 2 Perform the power-on check, as shown in Figure 3-20.
Figure 3-20 Power-on check of the eA360
Issue 01 (2014-07-30)
Check Item
When the eA360 is mounted on a metal utility pole, the fixture must
be firmly installed, and the CPE must be attached.
When the eA360 is mounted on the wall, the installation hole on the
fixture must be aligned with the one on the expansion bolt. In addition,
the fixture must be tightly and firmly attached to the wall and must not
wobble when you shake it.
Check Item
No cable is short-circuited or inversely connected.
The connector of the PoE network cable must be appropriately
connected.
The waterproof connector of PoE must be tightened.
Huawei Proprietary and Confidential