Vertical Terminations - DuraVent polypro Installation Instructions Manual

Single-wall gas vent system for category ii & iv gas-burning appliances
Table of Contents

Advertisement

Stainless Horizontal (Fig.15)
1.
Cut opening in the wall.
2.
Add Trim Plates and locking band (if
applicable) to final pipe length before
installing. Make sure flanges are facing
towards the wall. Use non-hardening
sealant where necessary.
3.
After exterior trim plate is mounted to
wall, measure 3" from exterior plate and
cut off female pipe end. Duburr. Seal
pipe to exterior plate. Slide Bird screen
over cut pipe end and tighten clamp.
EXTERIOR PLATE
CUT LINE
BIRD
CLAMP
SCREEN
Figure 15
Figure 16
THROUGH HOLE SIZING
4PPS: 4.125"
5PPS: 5.25"
6PPS: 6.125"
8PPS: 8.00"
FLANGES
INTERIOR PLATE
PP PIPE
CENTERLINE OF
EXHAUST OUTLET
OF APPLIANCE
INITIAL
FINAL
Vertical Concentric (Fig.17)
Locate penetration. (Fig.16)
1.
Cut hole in roof. (Table 3)
2.
3.
Cut hole in ceiling above appliance.
4.
Firestop each ceiling penetration.
Attach flashing to roof. (Fig.17)
5.
6.
Slide vertical termination into flashing
from above until seated on flashing.
7.
Plumb Termination and mount support
bracket to structure.
TERMINATION
CAP
STORM COLLAR
FLASHING
SUPPORT CLAMP
Figure 17
EXHAUST
Figure 18
Cut hole(s) big enough for pipe in all
ceilings above appliance if installing
in a multi story installation.
Slide storm collar onto flashing if
using the Adjustable Roof Flashing.
AIR INLET
11