Set-up and Initial Commissioning
8
Initial start-up
.04
8
Switching the machine on / off
.05
O Switch the machine on (see chapter 7.01 Main switch).
8
Checking the start inhibitor function
.06
O Switch on the machine at the main switch and move the sewing head.
O If the message does not appear, check the start inhibitor setting as explained in chapter
O Right the sewing head and acknowledge the error message.
24
Fig. 8 - 06
Never operate the machine if there are any differences.
The machine must only be connected to a grounded socket!
The error message "ERROR: 9" must appear in the control panel.
8.01.03 Assembling the start inhibitor.
The machine is ready for operation again.
O Remove the plug 1 of the oil reservoir 2
before the initial commissioning.
1
O Inspect the machine, particularly the
electric cables, for any damage.
O Clean the machine thoroughly, see also
chapter 12 Maintenance and Care.
O Arrange for technical staff to check
whether the machine's motor may be
operated at the existing mains voltage
2
and whether it is connected properly.
Danger of machine damage!
The plug 1 serves solely for
transit support and may not be
used during the sewing opera-
tions.