Guidelines When Installing The Drain Piping - Daikin FCAHG71FVEB Installation And Operation Manual

Split system air conditioners
Hide thumbs Also See for FCAHG71FVEB:
Table of Contents

Advertisement

5 Installation
a
b
c
710
d
840
e
860~910
f
950
a
Drain piping
b
Refrigerant piping
c
Hanger bracket pitch (suspension)
d
Unit
e
Ceiling opening
f
Decoration panel
A
B
C
A
Ceiling opening
B
Distance between the unit and the ceiling opening
C
Overlapping between the decoration panel and the
suspended ceiling
▪ Installation guide. Use the installation guide to determine the
correct vertical position.
A
a b c
A
In case of installation with standard decoration panel
B
In case of installation with fresh air intake kit
C
In case of installation with self-cleaning decoration panel
a
Suspended ceiling
b
Installation guide (accessory)
c
Unit
▪ Level. Make sure the unit is level at all four corners using a level
or a water-filled vinyl tube.
a
b
b
a
Level
b
Vinyl tube
c
Water level
NOTICE
Do NOT install the unit tilted. Possible consequence: If
the unit is tilted against the direction of the condensate flow
(the drain piping side is raised), the float switch might
malfunction and cause water to drip.
Installation and operation manual
6
(mm)
If A
Then
B
C
860 mm
20 mm
35 mm
(= min.)
910 mm
35 mm
20 mm
(= max.)
B
C
c
5.1.2
Guidelines when installing the drain
piping
Make sure condensation water can be evacuated properly. This
involves:
▪ General guidelines
▪ Connecting the drain piping to the indoor unit
▪ Checking for water leaks
General guidelines
▪ Pipe length. Keep drain piping as short as possible.
▪ Pipe size. Keep the pipe size equal to or greater than that of the
connecting pipe (vinyl pipe of 25  mm nominal diameter and
32 mm outer diameter).
▪ Slope. Make sure the drain piping slopes down (at least 1/100) to
prevent air from being trapped in the piping. Use hanging bars as
shown.
1~1.5 m
a
Hanging bar
O
Allowed
X
Not allowed
▪ Rising piping. If necessary to make the slope possible, you can
install rising piping.
▪ Drain hose inclination: 0~75  mm to avoid stress on the piping
and to avoid air bubbles.
▪ Rising piping: ≤300  mm from the unit, ≤675  mm perpendicular
to the unit.
a
b
≤300
a
b
a
Metal clamp (accessory)
b
Drain hose (accessory)
c
Rising drain piping (vinyl pipe of 25 mm nominal diameter
and 32 mm outer diameter) (field supply)
d
Hanging bars (field supply)
▪ Condensation. Take measures against condensation. Insulate
the complete drain piping in the building.
▪ Combining drain pipes. You can combine drain pipes. Make
sure to use drain pipes and T-joints with a correct gauge for the
operating capacity of the units.
a
T-joint
a
1000~1500
c
d
d
a
(mm)
FCAHG71~140FVEB
Split system air conditioners
4P429472-1 – 2015.12
(mm)

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fcahg100fvebFcahg140fvebFcahg125fveb

Table of Contents