Planning the grounding of the cable shields at the cabinet
lead-through
Follow the principle shown below when planning the grounding of the cable shields at the
cabinet lead-through.
1
2
3
4
1
To power cable terminals
2
Cable shield
3
PE (ground) terminal of the cabinet, cabling panel or
drive module
4
Stripped part of the cable
5
EMC sleeve
6
Lead-through plate
7
Base plate
8
Strain relief
9
Conductive shielding cushions for control cables
5