1.
Display: The digital read out displays the ambient tempera-
ture, set point and remaining time in minutes. It is also used
to display diagnostic error codes.
2.
Steam Icon: When illuminated the steam cycle is running.
3.
Water Icon: When steam shower is not in use the blue water
waves indicate the InstaMist feature is on. This is also
illuminated when the steam bath cycle is running.
4.
Time / Temp button: Used to program the default timer when
the steam bath is off. Adjustments are made with the
Up/Down buttons. The button will switch between time and
temperature when the steam bath is on. Adjustments to the
timer made during a steam bath cycle are temporary. All
temperature adjustments are held in memory for the user of
the cycle that is running.
5.
IM/Stop button: Toggles the InstaMist feature on/off when
the steam bath is off and stops the steam bath cycle when a
cycle is started. InstaMist is a preheat function that keeps the
water heated for quick starts.
6.
User 1 button: Starts the user one cycle and is the up
function while in cycle.
7.
User 2 button: Starts the user two cycle and is the down
function while in cycle.

Installation Instructions

1.

Pre-Installation - Control Location

a) The TSC-250 Control must be installed inside the steam
room. For convenience the recommended height from
the floor is four feet. Provide a 1½" hole in the wall at
this location (see Figure 1).
IMPORTANT: Multi-conductor cable must be installed so
that the end will not be buried inside the wall. The unit
will not operate unless the control is installed.
2.

Electrical Rough-in

a) Remove the multi-conductor cable from the control
packing box. Carefully route the multi-conductor control
cable from the steam generator to the TSC-250 located
inside the steamroom (see Figure 2). Route multi-
conductor cable through a ¾" conduit to protect the
cable from damage and to facilitate replacement if
necessary.
WARNING: Elderly persons, pregnant women, or those suffering from heart disease, high blood pressure, diabetes, or
who are otherwise not in good health, do not use this device unless directed to do so by a physician. Also, do not use
!
steambath while under the influence of alcohol. For additional Important Safety Information, please see a separate
instruction sheet Pub. No. 199.
IMPORTANT: The TSC-250 Control will only function with the current TSG steam generators.
06/10
®
TSC-250 Digital Temperature Control
1
4
6
IMPORTANT: This control must be installed inside the
steam room for proper operation of the system.
Cleaning Instructions: Use a damp cloth and mild soap.
Do NOT use abrasive cleaners which might scratch the
surface or the base of the control.
Figure 1
IMPORTANT: Run the
Control Cable through
a ¾" conduit.
Inside Installation:
TSC-250 Control.
Locate away from
the direct line of
shower spray and
do NOT locate
above steamhead.
1½" Hole
located four feet
from the floor
- 1 -
Installation and Operating Instructions
Model: TSC-250
TIME
IM
1
2
TEMP
STOP
To Steam Generator
Coupler
Double-Sided
Adhesive Pad
Pub. No. 271-A
C
US
®
2
3
5
7

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TSC-250 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Steamist TSC-250

  • Page 1 Also, do not use steambath while under the influence of alcohol. For additional Important Safety Information, please see a separate instruction sheet Pub. No. 199. IMPORTANT: The TSC-250 Control will only function with the current TSG steam generators. 06/10 Pub. No. 271-A...
  • Page 2 After the control is in place, apply silicone (supplied) around the control to form a watertight seal (see Figure MPORTANT: The adhesive on the back of the TSC-250 control will NOT seal this control. It is the responsibility of the installer to seal this control to the wall with the supplied silicone.
  • Page 3 Installation and Operating Instructions Installation Instructions Model: TSC-250 Installation Instructions for Steamhead & Figure 6 - Center Hub Installation Center Hub Make sure the 3/4" nipple protrudes beyond the tile IMPORTANT: Install top first approximately 1/2" (see Figure 5). Wrap the nipple with pipe sealant tape.
  • Page 4 Generator error codes are not covered in this document. Figure 7 - Installation Suggestions TSX-220 Auxilary Outside Control TSC-250 or TSC, TSC-350 inside control required. Locate away from the direct line of shower spray and do NOT Steamhead Installation locate above steamhead.

Table of Contents