Installation location
NOTICE
Installation location
The module must be installed so that its upper and lower ventilation slits are not covered,
allowing adequate ventilation. Above and below the device, there must be a clearance of 25
mm to allow air to circulate and prevent overheating.
Remember that the permitted temperature ranges depend on the position of the installed
device.
Device position / permitted temperature range
Horizontal installation of the rack:
-20 °C to +70 °C
Vertical installation of the rack:
-20 °C to +60 °C
4.3

Installing, connecting up and commissioning

Requirement: Configuration prior to commissioning
One requirement for the commissioning of the module is the completeness of the STEP 7
project data (see below, step 5). You should also read the section "Ethernet interface (X1) >
Advanced options (Page 43)".
Installing, connecting up and commissioning the module
Note
Connection with power off
Only wire up the S7-1200 with the power turned off.
CP 1243-1 DNP3, CP 1243-1 IEC
Operating Instructions, 02/2014, C79000-G8976-C312-02
Installation, connecting up, commissioning
4.3 Installing, connecting up and commissioning
Installation location
29