SunTouch System Installation Steps Summary
The recommended SunTouch system installation steps are:
Review, prepare and install SunTouch Power Center (pages 44): Review high voltage connections.
1
Prepare and install the SunTouch Power Center at the equipment pad. AC power for SunTouch should be
provided from the main-panel circuit breaker located at the house.
Remove SunTouch Power Center knockouts, install conduit and low voltage wire to the Power
2
Center (page 48).
Install Auxiliary Relays and Valve Actuators (page 53-55): Install auxiliary relays, valve actuators,
3
and connect actuator cables to the SunTouch motherboard (VLV A, VLV B, or VLV C).
Install Temperature Sensors and Heat Thermostat (page 56): Install water and air sensors.
4
Connect sensor cable plugs to the SunTouch motherboard.
Optional Equipment - Connecting IntelliChlor and IntelliFlo 4x160 pump (page 51): Connect the
5
IntelliChlor and IntelliFlo 4x160 communication cable to the SunTouch motherboard to connector COM
PORT.
SunTouch System Start-up (page 60): Perform a system start-up procedure.
6
Setting up SunTouch after equipment installation via main menu (page 61): Configure the
7
SunTouch control panel via the main menu for installed equipment.
Required Tools
•
3/16 in. diameter drill (for mounting the SunTouch Power Center)
•
5/16 in. diameter drill (for mounting water temperature sensor)
Installation and Setup
SunTouch Pool and Spa Control System Installation and User's Guide
37
Section 2