Final Check and Trial Operation

22
E-
AVXWN@@_IM_E_31755_5.08.10.indd 22
To complete the installation, perform the following checks and tests to ensure
that the air conditioner operates correctly.
1
Check the following:
Strength of the installation site
Tightness of pipe connection to detect gas leak
Electric wiring connection
Heat-resistant insulation of the pipe
Drainage
Grounding conductor connection
Correct operation (follow the steps below)
2
Press the
button and check the following:
The indicator on the indoor unit lights up.
The airflow blade opens and the fan gears up for operation.
3
Press any button and check the following:
 T he appropriate indicator lights up and the air conditioner operates
according to the selected mode or function.
4
Press the
button and check the following:
The airflow blades work properly.