ES3000 Ethernet Switch - Quick Install Guide
Installation

Preparing for Site Installation

Site preparation for the ES3000 Ethernet Switch installation begins with a site survey and network
analysis. Review the site survey reports to determine specific equipment placement, site-specific port
capacity and power drops. Ensure the installation area is free of dust and dirt.
Review the following guidelines for site preparation:
• Assign installation responsibility to appropriate personnel.
• Identify where all installed components are located.
• Verify appropriate rack mounting requirements.
• Arrange for a sufficient number of power drops to support the equipment installation.
• Verify adequate ventilation to all installed equipment.
• Identify and prepare Ethernet and TCP/IP and serial port connections.
• Verify cable lengths are within maximum allowable distances for optimal signal
transmission.

Package Contents

Inspect the package contents and report any missing or damaged items to the Symbol sales
representative. The package (for both the PoE and non-PoE Ethernet Switch models) should contain
the following:
• ES3000 Ethernet Switch
• Quick Installation Guide
• Rack-mounting brackets
• Power cord (optional)