Installing The Outside Terminal - Slant/Fin EUTECTIC EC10DV Series Installation Instructions Manual

Direct vent oil-fired water boiler
Hide thumbs Also See for EUTECTIC EC10DV Series:
Table of Contents

Advertisement

TRDV SERIES

INSTALLING THE OUTSIDE TERMINAL

The maximum wall thickness shall be no more than 356mm (14 in). Contact Slant/Fin for recom-
mendation in case of a thicker wall.
The system is not designed for common venting. Use for a single appliance only.
Use Figure 6 and Figure 7 to complete the following steps.
1. Determine the terminal location.
2. Cut 210mm (8-1/4in.) diameter hole through the wall (slightly
larger than the O.D. of the terminal)
3. Pull apart the inner and outer terminal sections.
4. Slide the outer wall plate over the outer section of the terminal
until it rests against the bead.
5. From the outside of the building, insert the outer section
through the hole until it resets against the wall.
FIGURE 6: Vent terminal installation into wall
FIGURE 7: Vent terminal mounting
6. From the inside of the building, slide the inner wall plate over
the outer and secure using the (4) screws.
7. Position the outer section so the seam on the flue collar is on
the top and the air intake on the bottom. Secure the outer
section by tightening the gear clamp around it. The gear clamp
is factory welded to the inner wall plate.
8. Seal with a weather proof sealant around the bead and edge of
the outer wall plate to prevent water from getting inside.