Sps stackable slimline converter shelf

Advertisement

Step 4 - Connect Shelf to Shelf Cables
1.
Install Data cables between adjacent power shelves -
J3-4.
2.
Install -24V Alarm Cable (provided) from 24V Alarm
Connector to J2 pin 3 (Aux Major) on the SPS shelf with
controller.
Step 5 - Set Shelf ID Jumpers
A maximum of 4 Rectifier and Converter shelves can be interconnected. Each shelf must have a unique ID.
Top Shelf
2nd Shelf
set to 1
set to 2
Step 6 - Connect Circuit Breaker Loads
1. Verify that breaker is OFF or not installed.
2. Remove detachable terminal block
3. Insert load and load return wires
Strip 0.4 in (10 mm)
8 AWG (6 mm
4. Torque to 6.5 in-lb (0.75 Nm).
5. Pull wires to verify.
6. Insert detachable terminal block fully.
Step 7 - Install Breakers
Install breakers into positions as specified in Site Engineering Instructions.
Use only breakers specified in the Slimline Power System Brochure.
1. Remove Cover (thumb screw).
2. Verify that each Breaker is OFF.
3. Insert each Breaker fully into its position — oriented with ON position at top.
4. Remove cover knockouts for installed positions.
5. Replace Cover (thumb screw).
6. Turn each Breaker ON.
2
Distribution
cable
Shelf ID
3rd Shelf
4th Shelf
set to 3
set to 4
) max.
2
SPS J2007003 L064 - Quick Start Guide
Document 850047442 r01 2015 July
Data
cable
+24V Load
Load Return
Distribution Shelf
L051C Shelf (ID=1)
(with controller)
24V Alarm Cable
L064 Shelf (ID=2)
(no controller)
Wire Entry
Screw
Detachable
Terminal Block