To install the frame, do the following:
Attention:
It is the service representative's responsibility to complete the following steps.
1. Before starting the installation, check all cable openings in the floor panel and location of the rubber
bushing holes so that they match the dimensions given in the following illustrations.
64.6 mm
654.8 mm
(2x) Opening for Cables
1220 mm REF
48 in REF
610 mm (24 Inch) Floor Tile Layout
2. Power off the system and make sure all cables and connectors are disconnected and are not
dangling around the frame. The frame should be free to roll.
50
Eserver pSeries 670 Installation Guide
(4x) 49.3 mm
Eyebolt
(2x) 450 mm REF