1) Safe, reliable operation of this boiler depends upon installation by a professional heating contractor in strict accordance
with this manual and the authority having jurisdiction.
• In the absence of an authority having jurisdiction, installation must be in accordance with this manual and the National
Fuel Gas Code, ANSI Z223.1.
• Where required by the authority having jurisdiction, this installation must conform to the Standard for Controls and
Safety Devices for Automatically Fired Boilers (ANSI/ASME CSD-1).
2) Read Section VI to verify that the maximum combustion air and exhaust pipe lengths will not be exceeded in the planned
installation. Also verify that the vent terminal can be located in accordance with Section VI.
3) Make sure that the boiler is correctly sized:
• For heating systems employing convection radiation (baseboard or radiators), use an industry accepted sizing method
such as the I=B=R Guide RHH published by the Air-Conditioning, Heating and Refrigeration Institute (AHRI).
• For new radiant heating systems, refer to the radiant tubing manufacturer's boiler sizing guidelines.
• For systems including a Crown Mega-Stor indirect water heater, size the boiler to have either the Heating Capacity
required for the Mega-Stor or the I=B=R Net Rating required for the heating system, whichever results in the larger
boiler.
• For systems that incorporate other indirect water heaters, refer to the indirect water heater manufacturer's instructions for
boiler output requirements.
4) Make sure that the boiler received is configured for the correct gas (natural or LP).
5) This boiler is not designed for use with return temperatures under 120F for a sustained period of time. Some systems, such
as those having large water contents, may require a return water bypass or other special provisions to protect the boiler
against low return temperatures. Failure to provide such provisions if needed could result in severe corrosion damage to the
boiler. For more information on when low water temperatures protection is required, and appropriate protection, see Part
VIII.
6) For installations at altitudes above 2000ft, special orifice and pressure switches are required. Make sure that the boiler is
configured for use at the correct altitude.
This product must be installed by a licensed plumber or gas fitter when installed within the Commonwealth of Massachusetts.
See Appendix A for additional important information about installing this product within the Commonwealth of Massachusetts.
FAILURE TO OBSERVE THE FOLLOWING LOCATION REQUIREMENTS COULD RESULT
IN A FIRE, EXPLOSION OR CARBON MONOXIDE (CO) HAZARD.
1) Boiler clearances are shown in Figure 4.1. Figure 4.1a shows clearances from the boiler when outdoor combustion air is
used. Figure 4.1b shows clearances from the boiler when combustion air is obtained from the boiler room. These minimum
clearances apply to all types of combustible construction as well as noncombustible walls, ceilings and doors. At least 24"
must be provided for servicing at the front of the boiler. This front clearance may be provided through a door, such as a
closet door. Boiler will be much easier to service if at least 12" is provided from the sides and rear of the boiler to walls.
2) Clearances from venting to combustible material depends upon the type of venting, whether the vent pipe is enclosed, and
whether the venting is vertical or horizontal. See Table 4.2 for vent clearance information.
3) Boiler may be installed on a non-carpeted combustible surface.
4) The relief valve must not be moved from the location shown in Figure 2.1.
5) When combustion air is obtained from the boiler room, a 10" clearance is required from the side of the boiler having the air
inlet collar to combustible or non-combustible obstruction (Figure 4.1b).

III Before Installing

NOTICE
IV Locating the Boiler
WARNING