12.3

Pump Down Operation

Purpose
Ensure the pump down operation when relocating or disposing of the unit. The pump down operation will extract all
refrigerant from the piping into the mono bloc unit.
Pump down operation control:
1
Press the SERVICE S/W for continuous 5 secs to enter Service mode.
2
In service mode, select Sr:01 and press SET S/W to start Pump Down operation.
3
There will be no Low Pressure error & Freeze prevention judgement during pumpdown operation.
4
3 ways valve will shift to room side.
5
Press the ON/OFF button to stop the unit.
12.4

Flow Switch

12.4.1 Flow Switch Control
1
The water flow switch serve as an overload protector that shuts down the unit when the water level is
detected to be low.
2
Detection is Lo (0V) when there is no water flow, and detection is Hi (5V) when there is water flow.
12.5

Force Heater Mode Operation

The backup heater also serves as backup in case of malfunctioning of the mono bloc unit.
1
Make sure the OFF/ON remote control LED is OFF (no operation).
2
Press the Force button to start the force heater mode operation.
3
During force heater mode, all other operations are not allowed.
4
Press OFF/ON button to stop the force heater mode operation.