Reconnecting the UPS
Use the following procedure to reinstall the UPS and transfer the critical
load from Maintenance Bypass (AC Line operation) to the UPS:
Powerware
®
Prestige Series Installation and Operator's Manual for IBM Applications (3000 VA) Uncontrolled Copy
1. Reconnect the battery cabinet to the battery connector on the
UPS rear panel.
2. Switch the circuit breaker on all battery cabinets to the ON (
position.
3. Steps 4 through 8 are for changing the output voltage. The
output voltage is factory-configured for 230V. If you do not
need to change the UPS output voltage, skip to Step 9. Use the
following table to select the correct output voltage according to
your PPDM.
PPDM Model Number
5-15R PPDM 208: 120/208
5-15R PPDM 208: 120/240
5-15R PPDM 208: 120
5-15R PPDM 240: 120/240
5-15R PPDM 240: 120
5-15R/6-15R PPDM: 208
5-15R/6-15R PPDM: 240
IEC 320-C13 PPDM
*
The UPS output voltage should be set according to local mains voltage.
4. Press and hold the Output
Y-cord of the PPDM into the power connectors on the UPS as
shown in Figure 17.
Release the Output
All indicators flash simultaneously.
UPS Voltage Selection*
Set to 220V for 110/220V PPDM output
Set to 230V for 115/230V PPDM output
Set to 240V for 120/240V PPDM output
Set to 220V for 110V PPDM output
Set to 230V for 115V PPDM output
Set to 240V for 120V PPDM output
Set to 220V for 220V PPDM output
Set to 230V for 230V PPDM output
Set to 240V for 240V PPDM output
Off button while plugging the
Off button when the alarm beeps.
UPS Operation
)
|
208
208
208
208
240
55
Need help?