Vent Clearances And Framing; Pipe Clearances To Combustibles; Wall Penetration Framing - Heat & Glo XLR-N-CE Owner's Manual

Hide thumbs Also See for XLR-N-CE:
Table of Contents

Advertisement

8 8

Vent Clearances and Framing

A. Pipe Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance to
vent. DO NOT pack insulation or other combustibles:
• Between ceiling fi restops
• Between wall shield fi restops
• Around vent system
Failure to keep insulation or other material away from
vent pipe may cause over heating and fi re.
Note: Heat shields MUST overlap by a minimum of 38 cm.
• SLP heat shield - designed to be used on a wall 11,1 cm to 19,4 cm thick.
• If wall thickness is less than 11,1 cm the existing heat shields must be field tricmed.
If wall thickness is greater than 19,4 cm a DVP-HSM-B will be required.
Heat
Shield
7,6 cm
top clearance
2,5 cm
clearance around
vertical sections
2,5 cm
bottom
clearance
Figure 8.1 Horizontal Venting Clearances To Combustible
Materials
30
6,4 cm
top clearance
Heat
Shield
1,3 cm
clearance
bottom & sides
Wall
Shield
Firestop
WALL
Heat & Glo • XLR-N-CE, XLR-PB-CE • 2198-900 Rev. N • 3/14
B. Wall Penetration Framing
Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must
frame a hole for the wall shield fi restop(s). The wall shield
fi restop maintains minimum clearances and prevents cold
air infi ltration.
• The opening must be framed on all four sides using the
same size framing materials as those used in the wall
construction.
• SLP pipe - A wall shield fi restop must be placed on each
side of an interior wall. A minimum 3,8 cm overlap of at-
tached heat shields must be maintained.
• See Section 10.K. for information for regarding the in-
stallation of a horizontal termination cap.
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncom-
bustible materials such as concrete, a hole with diameter
2,54 cm greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield fi restop is only required on one side and no heat
shield is necessary.
DO NOT PACK WITH
INSULATION OR
OTHER MATERIAL
25,4 cm
25,4 cm
A
A*
122 cm
* Shows center of vent framing hole for top venting. The center of the hole
is one 2,54 cm above the center of the horizontal vent pipe.
Figure 8.2 Wall Penetration
B
B
120 cm

Advertisement

Table of Contents
loading

This manual is also suitable for:

Xlr-pb-ce

Table of Contents