Expansion board installation into slot 2
o
Expansion board installation into slot 3
o
Connect all necessary internal cabling to the expansion board. For more information on these cabling
9.
requirements, see the documentation that ships with the option.
Install the PCI riser cage (on page 24).
10.
IMPORTANT:
Install the access panel (on page 22).
11.
Install the server into the rack
12.
Power up the server (on page 17).
13.

M.2 SSD enablement option

To install the component:
Power down the server (on page 17).
1.
Remove all power:
2.
Disconnect each power cord from the power source.
a.
The server does not power up if the PCI riser cage is not seated properly.
("Installing the server into the
rack" on page 30).