Preparing for installation
Requirements regarding on-site connections
C DHW circulation
D Opening for 230 V cables
E Cold water
F Liquid line
Connection sizes for hydraulic connections
Pos.
Sym-
Meaning
bol
B
–
DHW
C
–
DHW circulation
E
–
Cold water
F
Refrigerant lines from/to
the external unit:
■ Liquid line
G
■ Hot gas line
H
Heating water flow
K
Heating water return
1. Prepare the connections on the heat-
ing water and the DHW side.
Flush the heating system.
8
(cont.)
G Hot gas line
H Heating water flow
K Heating water return
Connections to the internal unit
7 connection pipe:
(supplied pipe bends)
UNF thread:
For type AWT-AC 221.A04, a reduction
from 10 to 6 mm is necessary down-
stream of the pipe bend (reducer ⅝ to ⁷⁄₁₆
supplied).
7 connection pipe:
(supplied pipe bends)
UNF thread:
For type AWT-AC 221.A04, a reduction
from 16 to 10 mm is necessary down-
stream of the pipe bend (reducer ⅞ to
¾ supplied).
2. Prepare the electrical connections.
Rp ¾
G 1
Rp ¾
10 mm
⅝
16 mm
⅞
Cu 28 x 1 mm
Cu 28 x 1 mm