3.1.4 Management VLAN Configuration
ERS8600-1: Step 2 – Add management IP address and add port members
ERS8600-1:5(config)# interface vlan 200
ERS8600-1:5(config-if)# ip address 10.12.200.12 255.255.255.0
ERS8600-1:5(config-if)# exit
ERS8600-2: Step 2 – Add management IP address
ERS8600-2:5# config vlan 200 ip create 10.12.200.13/24
ERS4550T-1: Step 2 – Add management IP address
4550T-1(config)# vlan mgmt 200
4550T-1(config)# ip address 10.12.200.14 netmask 255.255.255.0
ERS4528GT-2: Step 2 – Add management IP address
4548GT-2(config)# vlan mgmt 200
4548GT-2(config)# ip address 10.12.200.15 netmask 255.255.255.0
C3750-1: Step 2 – Add management IP address
C3750-1(config)# interface vlan 200
C3750-1(config-if)# ip address 10.12.200.10 255.255.255.0
C3750-1(config-if)# exit
C3750-2: Step 2 – Add management IP address
C3750-2(config)# interface vlan 200
C3750-2(config-if)# ip address 10.12.200.11 255.255.255.0
C3750-2(config-if)# exit

3.2 Verify Operations

3.2.1 Verify CIST Root
Step 1 – Verify that the CIST root and CIST Regional root is C3750-1:
ERS8600-1:5# show spanning-tree mstp status
RSTP/MSTP Technical Configuration Guide